Net Zero Energy Certified
It’s official, we received our CHBA Net Zero certification label this week! Big thanks to capitalhomeenergy and twinlionscontracting for handling the paperwo...
It’s official, we received our CHBA Net Zero certification label this week! Big thanks to capitalhomeenergy and twinlionscontracting for handling the paperwo...
We had record amounts of rainfall on the North Shore this past weekend in the first ‘atmospheric river’ of the season. Over 250mm of rain (>10”) 🤯 fell ov...
Superposition, 2022 by james.nizam with galleryjones. We offered up our 1958 house as a canvas before deconstruction, and the results were extraordinary. Fas...
A few photos from the garden taken over the last couple of weeks. We had a fair bit of time pressure to get all initial planting done before our move date to...
At long last! Excited and very relieved to be in our new place and at the end of a long journey. Cheers to the team at Twin Lions, especially Morgan, Fish an...
Final few days of tweaking, touch ups and inspections. We spent the morning getting a run-down on our heat pump, HRV and heat-pump water heater. We were able...
“This house produces more energy than it uses on an annual basis”.
Closing out summer with final paint colours, heat pump installed, sod and stepping stones laid, and fireplace complete.
Our solar team @puresolarcanada stopped by the house last week to switch on our panels. A big moment - we are now live and producing clean on-site electricity!
Lots of action on site this week as we complete the driveway and hardscape. Because of the site’s poor drainage (see Stormwater Management post 11/24/2023), ...
The kitchen. So many hours spent here cooking, socializing, prepping lunches, baking cookies, making preserves, packing for adventures. We wanted to create a...
Lots of metalwork in recent days…
Tiles are in and looking fine!👌 Select cabinets as well - top quality work from @millwerks. Blind selection is underway. We must be in the home stretch? Huge...
Cedar soffit install has been progressing nicely with scaffolding moving about the house one side at a time.
It was a shoes off kind of site visit over the weekend with oak flooring in place 👌Look at the the detail on that stairwell! We went with hardwood upstairs /...
The team has been working hard to get all our Hardie siding up. It’s looking fantastic - just the final sections to go at the soffit line.
Today’s the day! 27 solar panels and 12.7MWh of annual production installed on the roof! A much anticipated moment and key part of the net zero equation. So ...
This week it’s all about drywall and siding. Heaters are going full blast in here to dry out the tape and joint compound. Siding is going up around the back ...
Happy Friday everyone! The majority of insulation is in and we’re onto drywall! It feels quieter and warmer in the house already.
@capitalhomeenergy stopped by this week to conduct a pre drywall blower door test.
We passed framing inspection this week! High fives to our team @twinlionscontracting for hitting this major milestone. We spent some time documenting what’s ...
If you have solar panels on your roof, it makes sense to add batteries too so you can store excess energy, help smooth out peaks in demand, and power the hom...
A ton of plumbing, mechanical and electrical work happening behind the scenes lately. As well as ‘back framing’ – final interior framing around bulkheads, do...
Our walkway, landing and front stairs are done! And with that, the last low-carbon concrete pour as well. Phew!
Lots of momentum while we’ve been away for spring break. Our house is now closed in and we have a key! ‘Lock-up’ means not only windows but doors in as well....
Big pruning work today to pull vegetation back from the roof ahead of solar install. Burley Boys Tree Service turned up bright and early to thin the canopy o...
We have rigid insulation going in on the ground floor slab this week (one of the advantages of increasing the ceiling height in the basement). Result will be...
With the framing progress this week, we were able to snap a couple close up photos of the air barrier system – the part of the home that will help keep our h...
Front deck is done, back deck sheathing goes on today. Closing out on interior framing too. Nice to see the rooms start to take shape.
Thrilled to see our triple pane windows by Vinyltek go in this week!
New front deck in progress 👏👏👏
The roof is sealed, our retaining wall is done, windows are taped up as the team breaks for the holidays. We took an evening walk past the house last night a...
In an earlier post, we discussed our HVAC strategy overall. For those interested in the nuts and bolts of system selection, air tightness and makeup air, thi...
You know you are closing in on sheathing completion when a site visit includes a roof-top walkabout!
This week, we’ve passed inspection on our stormwater management system. This is a District requirement, targeting new builds and homes adding significant sur...
We’ve been working with our project team to narrow down our HVAC strategy for the house. With upped insulation in the walls, high performance windows and air...
Sundays are for site visits and offcut finds!
Perfect conditions to raise the roof!!
Tons work in prep for roof arrival next week. We can almost recognize the house again 😲
Our floor sheathing is complete and main floor framing is going back up!
Another couple of weeks and the makings of a ground floor! Loving these engineered floor joists, parallel strand (PSL) beams and old studs sandwiched between...
Really great progress while we’ve been away. Nice to see some framing starting to take shape. A mix of new lumber, old lumber and parallel strand lumber (PSL...
It’s pour day!!! After a long stretch of sunny weather, it’s drizzling the day we pour concrete 🌧. We’ve opted for a low-carbon mix supplied by Rempel Bros /...
Quick work from our project team to get trades back on site 👍 We’ve been digging, cutting, and forming for foundation upgrades. Concrete scope includes: U...
We have a building permit in hand at long last. All further dispatches will be from site.
We thought we’d be back to work on site by now. Unfortunately, the final go-ahead is still held up because we have been going through a Wildfire Development ...
Haven’t posted anything in a while. We have been navigating the permitting gap between a deep energy retrofit and a new build.
An update - In the last 3 weeks, we’ve bolstered our engineering capacity and come up with a plan to tie into the existing foundation 🙌.
We’ve needed to pause work as a decision taken by BC Housing as to whether our project remains a renovation or has tilted in the new build category. No major...
As a renovation project above a threshold value, the District required us to upgrade the street utility connections. Here is the storm & sewer being repl...
We are nearing completion of our life cycle assessment (LCA). Overall it’s been an interesting process to learn what our highest carbon materials are, lower ...
This week is all about trenching for drainage and below grade plumbing. It’s been a very wet few weeks (North Van, what can you do!) but at least the tempera...
Throwback to September when we partnered with @galleryjones and artist @James.Nizam who turned our red room into a work of art 🙌
New year and things are now moving quickly. We have a digger on site! Have started to pull out the harder materials: front steps pebbledash walkway fo...
In celebration of the season here is a Christmas greeting from ChatGPT. Prompt was “A short Christmas Poem about an Energy Efficient Building”
Deconstruction has been moving swiftly. Our roof is off, the back deck is dismantled and our backyard shed too.
Our house has been stripped back to the basics! A few things seen on our site walkthrough:
It’s taken ages to get all the asbestos out of the house, but we passed air clearance on Friday ✅✅ which means our team can get started on the work proper.
Embodied Carbon in buildings refers to “greenhouse gas emissions arising from the manufacturing, transportation, installation, maintenance, and disposal of ...
Today’s milestone was that we had temp power added to our new electrical pole. A few big tree branches had to be pruned to accommodate this (sorry neighbors!...
Fences are up! Place is officially looking like a building site. We managed to salvage a few final items before handing over the house:
So awesome to be able to support this project ahead of our reno.
Breaking news, we have a permit in hand! Donuts, bubbly and thumbs up all round! Can’t wait to finally get started on this project. It’s taken us a year + 3 ...
We will need to redo a number of District connections as part of our renovation including water, sanitary and perhaps storm. This is at the cost of the owner...
Today we made some major progress on cleaning up the yard in preparation for construction. Evergreens were pruned, plants along the perimeter of the house pa...
No permit yet but much progress on interior design 👍 So grateful to be working with @tripledotdesignstudio to help streamline decisions. Who knew grout colou...
There are two things in life that, as adults, we don’t have any control over:
We inherited an old cast iron wood burning stove with the house, a Vermont Castings Resolute. Solid stove but would need a bunch of work & parts to get i...
While this account mainly focuses on net zero building, we are also doing a full gut renovation which means we have about 1000 decisions to make!
Yesterday, Fortis came by and disconnected the gas.
going to a good home
Exciting things underway in our red room as we await permit! With artist @james.nizam
Testing exterior paint colours before deconstruction
Our permit is moving along and we are getting closer to go time! Anticipated start date is mid-September.
The province and Canada have different funding available for energy efficiency retrofits.
image cred @sarahlazarovic
…with some plant photos!
This week we’re looking at windows and two performance metrics in particular: 1) U value, or USI in metric (inverse of R value). Measures the insulation or t...
Long post! TLDR, we can hit net zero with our design. See our Net-Zero Energuide Report and CHBA Net-Zero Energy Design Summary.
Our hazardous materials survey showed many materials containing asbestos - flashing, duct tape, firestop, vinyl floor tile, drywall joint compound and putty ...
We’re targeting a deep energy retrofit with a stretch goal of net zero. Why? After transportation (road & air) and “stuff” we consume, our home represent...
The current roof is hand framed, with an addition out back ~1970s. Structural upgrades would be needed to support solar for net zero + if we were to add insu...
Earlier this year, we went down the path of a detailed cost estimate for our net zero renovation that came back >2x our budget and timeline. Cue many late...
A blower door test measures how well the building envelope prevents air leakage. The fewer air changes per hour (ACH) the more airtight the building.
We had an energy audit conducted in March 2022. See our Baseline Energuide Report. Our energy performance was estimated at 185GJ/year, or 0.74 GJ/m2/year, wh...
What we like about the property is the location, solar access (yes, in North Vancouver!) position on the street, and views north and south.
Our house is a 1958 hip roof, wood framed house, with single pane aluminum windows, natural gas heating and hot water, and minimum insulation as was required...